Trevor & Dewey's RV-7 Construction Log
 
 

Wings - Fuel Tanks

Back to Log Index

Date: 2/16/2010
Time:
4.0
Task: Riveted nutplates on inner right spar, fabricated T-705

Riveted the K1000-3 nutplates on the inner part of the right spar for the T-712 Z-bracket.




Then I drilled the CVA-110 drain.




Started fabricating the T-705 bracket today for the right tank. The bottom is finished, now working on the top part (as seen in the picture).




After lots of cutting and sanding, one half of the top part is finished.