Time:
3.0
Task: Worked on bottom wing skins

Today we finished hole deburring the bottom wing skins. We then spent most of the evening dimpling all the skins and started edge burring the two outboard skins. I had a chance to apply RTV to the left wing electrical conduit as well. This should help prevent chaffage.